FAT and SAT: The Security Test You Already Have on the Calendar
Auditors, insurers and boards now ask the same question: how do you know? A policy says what should happen. A signed test record shows what did happen.
Every automation project already produces signed test records at two points. The Factory Acceptance Test (FAT) proves the system works at the supplier’s shop. The Site Acceptance Test (SAT) proves it works in your plant. Both are scheduled, staffed and taken seriously by engineering. Add a security page to each and they become some of the strongest assurance evidence a CISO can have, at almost no extra cost.
Why commissioning is a unique window
During commissioning the system is fully documented, the people who built it are on hand, and production doesn’t depend on it yet. All three disappear at go-live.
A misconfigured account found at FAT is a five-minute fix by the engineer who made it. Found two years later, it’s a change request, a maintenance window and an exception for your team to track. Commissioning is when findings are cheapest to close and least disruptive to the plant.
There’s a relationship benefit too. Running endpoint protection, logging and network rules during FAT shows, under real process conditions, that security controls don’t interfere with production. That one demonstration can do more to build trust with operations than any number of meetings.
The security page: ten checks
Give engineering a standard page they can drop into existing protocols. Five checks for FAT:
- Accounts: every account named and role-based, with no default or shared passwords.
- Hardening: the checklist from your spec appendix (Part 2) is complete and signed by the supplier.
- Versions: firmware, software and OS versions recorded for every component.
- Protections on: performance tests run with endpoint protection, allowlisting and logging enabled.
- One restore: a backup restored using the supplier’s written procedure, and timed.
Five checks for SAT:
- Paths match design: connections match the approved zone sketch from Part 1.
- Remote support demonstrated: the vendor connects through the approved access path and the session is logged.
- Leftovers removed: temporary wireless, cellular modems and “startup only” firewall rules are gone.
- Keys handed over: commissioning passwords changed and administrator credentials transferred to the owner.
- Logs arrive: events from the new system reach your SOC or monitoring platform.
Failed items go on the project punch list next to mechanical and electrical items, with an owner and a date. Security doesn’t need its own tracker. It needs a place on the one everyone already uses.
Staff it and scale it
The page is only as good as the person checking it. For larger systems, have someone from your OT security team, or a trusted partner, attend at least part of FAT and SAT. For a small packaged skid, the project engineer can complete the page and send it to your team for review.
Scale effort to what matters most. Ask what the line can’t run without (the question behind our stop-the-line map) and focus there. As we wrote in Agile OT Assessments That Fit Plant Schedules, the best checks fit the work already underway.
What it gives you to report
Once the page is standard, two measures fall out of it: the share of OT projects that completed security checks at FAT and SAT, and the share of findings closed before handover. Both trend over time, and a board can read them at a glance. They show security is built into how the company delivers new capacity.
What you can do now
Ask engineering which commissioning events are scheduled in the next two quarters across your plants. Pick one and offer the ten-check page above for its FAT and SAT protocols, and arrange for someone from your team to attend. Afterward, record how long the checks took and what they found. Bring those results to your engineering counterpart as the case for making the page part of the standard commissioning template, and start reporting the two measures above.
Next in the series: Part 4, “Handover Day,” covers the turnover package that brings every new system into your security program from its first shift.